1 Bio-methane potential from gasification of wooden biomass or How to get a tree into a pipe? by Anders Hedenstedt CEO, Göteborg Energi AB

2 Biogas in Gothenburg perspective Fulfilling our vision: Göteborg Energi shall actively contribute to the development of a sustainable Göteborg

3 Gas for three different markets. CHP Industry Vehicles Gas based CHP replaces electricity produced in coal condense units Gas replaces oil Gas replaces gasoline and diesel

4 Green gas principle Huge synergy effects arise when distributing biogas in the natural gas grid. (Market, summer surplus, security of supply, step by step) Biogas Upgrading Industrial processes Heat Natural gas Biogas as fuel

5 Potential Big Markets within 5 years

6 Existing and planned gas filling stations Karlstad Åmål Lidköping Örebro (1)+1 Strömstad Skara Tanum Vänersborg Trollhättan Uddevalla Lilla Edet Skövde Stenungsund Kungälv Alingsås Lerum Falköping Partille Huskvarna Göteborg (8) + 3 Mölndal Ulricehamn Mölnlycke Kinna Nässjö Borås Kungsbacka Varberg Gislaved Värnamo Falkenberg Halmstad Båstad Laholm Höganäs Ängelholm Helsingborg (3) Landskrona Lund Malmö (4) = existing gas filling stations = stations under construction Uppsala Västerås Arlanda Stockholm (7) + 4 Södertälje Eskilstuna Katrineholm Nyköping Norrköping (3) Mariestad Linköping (5) Motala Västervik Mjölby Jönköping Gnosjö Kalmar Olofström Hässleholm Åstorp Kristianstad (2) Eslöv Ystad Planned stations in northern Sweden: Boden, Skellefteå och Östersund

7 LCMG filling stations are under discussion Flexible filling station: Liquified gas(methane) can be filled as liquified gas or as compressed gas Filling of CMG LMG-tank Layout Cryostar Filling of LMG

8 Fermentation is an important but limited resource Cleaning Gas user Raw material Fermentation Gas network

9 Project Biogas Arendal Fermentation of sludge from wastewater treatment plant Removal of CO2 increases calorific value from 6 kwh/nm3 to 11 kwh/nm3 The plant is in operation since January 2007 Production of biogas: GWh/year

10 At least 5 TWh forest residues in west Sweden Transport costs: Truck Train Boat 20 /100 km 20 /1000 km 20 /10000 km Strömstad Tanum Sotenäs Lysekil Munkedal Orust Tjörn Kungälv Dals-Ed Mellerud Färgelanda Vänersborg Uddevalla Grästorp Trollhättan Vara Lilla Edet Stenungsun d Ale Bengtsfors Lerum Borås Öckerö Partille Göteborg Bollebygd Härryda Mölndal Åmål Essunga Götene Lidköping Skara Vårgårda Herrljunga Alingsås Falköping Ulricehamn Gullspång Mariestad Töreboda Karlsborg Tibro Skövde Hjo Tidaholm Gothenburg is well situated everything on the map is within 200 km from Gothenburg! Mark Svenljunga Tranemo

11 GoBiGas Gothenburg Biomass Gasification Project

12 Purpose and objective The purpose of the project is to demonstrate the possibilities of the gasification technology on a commercial scale, and to build a gasification unit that produces renewable and CO2-neutral gas. The objective of this is to take a significant step towards Göteborg Energi AB s long-term target to replace the natural gas in our own plants and meet our customers demand for renewable gas.

13 Project - GoBiGas Thermo-gasification of biomass and production of bio-methane Commercial scale approximately100 MW gas Production of high-calorific gas by methanation for distribution on the gas grid Also possible use as a CHP-fuel in Rya First part is planned to be in operation by the end of 2011

14 Production of bio-methane for different purposes and customers Processes Rya CHP Heating Fuel handling Gasgrid Gasification Cleaning Cleaning Vehicle fuel Methanation Compression Drying

15 Biomass to synthetic natural gas (SNG) based on indirect(allothermal) gasification Güssing

16 Chalmers University of Technology Biomass Gasification Project Circulating fluidized bed (CFB) Heat, Electricity, Steam Heat, Electricity, Steam Flue gas Flue gas Bio Product Gas Fuel Hot bed material Hot bed material Biomass Air Avdelningsnamn Air Fluidization gas (Steam or Bio Producer Gas or ) New concept Henrik Thunman Division of Energy Conversion

17 GoBiGas

18 GoBiGas

19 LNG in Gothenburg-vision Railway Natural gaspipe Norway, 50 bar Lowpressure-NG (100 mbarg & 4 barg) LNG-trailer Import/Export LNG-production ton/year 66 MW/560 GWh LNG-storage in rock m 3 LNG-boats Import/Export/Bunkering GoBiGas-boats Biogasproduction from sewage sludge GoBiGas gasification Rya CHP

20 Current activites in GoBiGas Detailed design for the first 20 MW (in operation end of 2011) Permits Supply of biomass Financing Discussions with interested partners

21 GoBiGas One plant many possibilities